Summary of protocol to establish a NRCS project through the GP-CESU


NRCS CESU Research Coordinator: 

Fred H. Reaves
CESU/Center of Excellence Coordinator
USDA/Natural Resources Conservation Service
P. O. Box 2890
Room 6227-South
Washington, DC 20013
Phone: (202) 720-1872  Fax:  (202) 720-4839
E-mail: Fred.Reaves@wdc.usda.gov

 

1)  Projects can originate from all levels of NRCS:  NHQ, Centers, States.


2)  Project must include a scope of work (proposal).  The proposal must include the following items:

  • Background of the Project

  • Timeline for the Project

  • Process for completing the task

  • Detailed Budget (indirect costs are limited to 10%)

  • Detailed list of Deliverables

3)  NRCS Project Manager works with Budget Officer to assure fund availability.

4)  Contract Modification must be completed, these can be requested from Fred Reaves (NRCS National CESU Coordinator), Fred.Reaves@wdc.usda.gov, 202-720-1872 (also available for download).


5)  Once completed, email the Modification and proposal onto Fred at NHQ.  Note:  the Modification must have the PI and Grant Administrator contact information completed.
 

6)  Fred will assure the proposal meets the requirements for the CESU, assign and log the modification number, and sign as the CESU Research Coordinator.
 

7)  The Modification will then be returned to the NRCS Project Manager (PO).
 

8)  The PO will work with the local Contracting Officer to secure the Principal Investigator and Grant Administrator signatures.   At this time, the University generates their internal tracking documents - PI-blue sheets, Grant Administrator-green sheets.
 

9)  When partner signatures are completed, the Modification is returned to NRCS for final signature.
 

10)  If the Modification is over $100,000, the Deputy Chief for Management must sign.  Fred will facilitate this signature.
 

11)  If the Modification is under $100,000, the host State Conservationist can sign.
 

12)  Budget Officer obligates funds.
 

13)  After signature from management, the Modification and budget obligation is complete and the work can begin.

 

*A copy of the Modification form MUST be submitted to the GP-CESU Administrative Coordinator

** Upon project completion, an electronic copy of the final report/deliverable MUST be submitted to the GP-CESU Administrative Coordinator

 

Please send all project modifications to the following address:

GP-CESU
Attn.Christine Lockert
University of Nebraska
514 Hardin Hall
Lincoln, NE 68583-0985
ph (402) 472-5853
fax (402) 472-2946
clockert2@unl.edu

 

 
                        

about us | project info | expert database | agency needs |
documents | news & events | home

If you have questions or comments concerning this web site,
 please contact the Webmaster.
Web Site Acknowledgments

The University of Nebraska - Lincoln does not discriminate based on gender, age, disability, race, color, religion, marital status, veteran's status, national or ethnic origin, or sexual orientation.
 

University of Nebraska - Lincoln
Institute of Agriculture and Natural Resources
College of Agricultural Sciences & Natural Resources
College of Arts & Sciences

University of Nebraska State Museum

Pioneering new frontiers.